To consider a report of the Director of
Economy, Transport and Environment seeking approval to progress the
implementation of the Camrose Link Road with an estimated cost of
£3.432 million funded by the Enterprise M3 Local Enterprise
Partnership , to change the detailed design of the Brighton Hill
roundabout improvement and to progress advance utility diversions
with an estimated cost of £1.77 million.