Decision Maker: Executive Member for Education
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
New 6FE secondary school Budds Lane, Bordon,
Hampshire
The decision:
a) That the Executive Member for Education gives approval to the project proposals for a new 6FE secondary school at Budds Lane, Bordon, at an estimated total cost of £29,990,000.
b) That the Executive Member for Education grants procurement and spend approval for contracting activity associated with the project as outlined in Section 3.4 and 3.5 of this report.
Report author: Jackie Rogers
Publication date: 19/06/2017
Date of decision: 19/06/2017
Decided at meeting: 19/06/2017 - Executive Member for Education Decision Day
Effective from: 27/06/2017