Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
Decision:
That Cabinet:
- Notes the £140m Tt2019 programme breakdown, the Department
targets and the headline programme timetable – section
3;
- Notes the Tt2017 delivery achievement, the positive position
reported in respect of Adults and acknowledges that there are no
legacy implications for the Tt2019 programme and therefore the
Tt2017 programme is formally closed – section 4;
- Notes the early opportunity assessment work completed by
Departments to this point and in particular acknowledges some of
the specific challenges of this programme including timing,
complexity and the inevitability of a changing service delivery
risk profile – section 5;
- Notes, per the programme timetable, the commencement in July of
a public consultation exercise aimed at helping to inform the early
autumn budget decision making process – section 6
Report author: Paul Archer
Publication date: 19/06/2017
Date of decision: 19/06/2017
Decided at meeting: 19/06/2017 - Cabinet
Effective from: 09/09/2017