Issue - decisions

Project Appraisal Vicarage Hill Hartley Wintney

30/11/2018 - Project Appraisal Vicarage Hill Hartley Wintney

1. That the Director approves the details of the Vicarage Hill in Hartley Wintney scheme, as set out in this paper.
2. That the Director gives approval to procure, spend and enter into necessary contractual arrangements to implement this scheme, at a total estimated cost of £196,000, to be funded from Developer Contributions.
3. That the Director approves a variation to the Capital Programme to reflect the increase in scheme value from £170,000 to £196,000. There are some additional carriageway repair works identified at the design stage.