To consider a report of the Director of Culture, Communities and Business Services that provided an update on major projects and issues currently being progressed within the department.

Decision:

That the Executive Member for Policy and Resources:

 

1.1      Progress of each of the programmes is noted.

 

1.2      That procurement and spend approval for contracting activity associated with the projects as outlined in this report is granted.

1.3    Approval is given the project appraisal to reclad the SCOLA Technology Block at Alderwood school at a total cost of £800,000 plus fees.(with fees is £932,000)

1.4    Approval is given to the project appraisal for the reclad of a SCOLA block at Applemore School at a total cost of £1,048,000 including fees.

1.5    Approval is given to the project appraisal for the reclad of the three storey block at Westgate School at a total cost of £1,048,000 including fees.

1.6    Approval is given to add essential maintenance works into the Library Transformation project at Totton Library with a revised total cost of £362,000 including fees.

1.7    Approval is given to the project appraisal (design and expenditure) on the basis set out in the report to facilitate the delivery of the Community Hub at Gosport Discovery Centre project at a total construction cost of £600,000 including fees.

 

 

Report author: Steve Clow

Publication date: 22/01/2018

Date of decision: 22/01/2018

Decided at meeting: 22/01/2018 - Executive Member for Policy and Resources Decision Day

Effective from: 07/02/2018

Accompanying Documents: