Issue - meetings

Harbour Works Consent Application – Brooklands Quay Mooring Buoy Relocation

Meeting: 13/07/2018 - River Hamble Harbour Board (Item 55)

55 Harbour Works Consent Application – Brooklands Quay Mooring Buoy Relocation pdf icon PDF 104 KB

To consider a report of the Director of Culture, Communities and Business Services setting out an application for Harbour Works Consent.

 

Additional documents:

Minutes:

(Councillor Keith Evans declared a conflicting interest as a member of the Planning Committee at Fareham Borough Council and left the room whilst this item was considered. Councillor Peter Latham chaired the meeting for this item only.)

 

The Board considered the report of the Director of Culture, Communities and Business Services setting out an application for Harbour Works Consent (Item 9 in the Minute Book).

 

It was confirmed that recommendation 1.1a (listed as ‘a’ below) had been incorporated following consultation with Natural England to ensure that the proposed mooring location be moved so that it is outside of the Solent Maritime Special Area of Conservation.

RESOLVED:

That the River Hamble Harbour Board approves Harbour Works Consent for the proposal set out in Section 4 of this report and subject to the following conditions:

 

  1. That the proposal is to be built in accordance with the details, plans and method submitted as set out in Appendix 1a and Appendix 1b, with the exception that the proposed mooring location is to be moved inshore so that it is located outside of the Solent Maritime Special Area of Conservation.

 

  1. That the final design of the mooring arrangement, location and the method statement for installation are to be submitted to and approved by the Harbour Master in advance of construction.

 

  1. That the maximum length overall of the vessel to be moored is to be 13 metres.

 

  1. That the existing mooring buoys located on the intertidal area within the creek are to be removed prior to installation of the new buoys.

 

  1. That all equipment, temporary structures, waste and/or debris associated with the licensed activities is to be removed upon completion of the licensed activities.

 

  1. That Harbour Dues are to be payable on any vessel occupying the mooring.

 

  1. That the development must be completed within 3 years from the date of the approval granted by the Harbour Board.

 

 


Meeting: 08/06/2018 - River Hamble Harbour Management Committee (Item 50)

50 Harbour Works Consent Application – Brooklands Quay Mooring Buoy Relocation pdf icon PDF 104 KB

To consider a report of the Director of Culture, Communities and Business Services setting out an application for Harbour Works Consent.

 

Additional documents:

Minutes:

The Committee considered the report of the Director of Culture, Communities and Business Services setting out an application for Harbour Works Consent (Item 8 in the Minute Book).

 

It was confirmed that recommendation 1.1a (listed as ‘a’ below) had been incorporated following consultation with Natural England to ensure that the proposed mooring location be moved so that it is outside of the Solent Maritime Special Area of Conservation.

 

RESOLVED:

 

That the River Hamble Harbour Management Committee recommends to the River Hamble Harbour Board to approve Harbour Works Consent for the proposal set out in Section 4 of this report and subject to the following conditions:

 

a.    That the proposal is to be built in accordance with the details, plans and method submitted as set out in Appendix 1a and Appendix 1b, with the exception that the proposed mooring location is to be moved inshore so that it is located outside of the Solent Maritime Special Area of Conservation.

 

b.    That the final design of the mooring arrangement, location and the method statement for installation are to be submitted to and approved by the Harbour Master in advance of construction.

 

c.    That the maximum length overall of the vessel to be moored is to be 13 metres.

 

d.    That the existing mooring buoys located on the intertidal area within the creek are to be removed prior to installation of the new buoys.

 

e.    That all equipment, temporary structures, waste and/or debris associated with the licensed activities is to be removed upon completion of the licensed activities.

 

f.     That Harbour Dues are to be payable on any vessel occupying the mooring.

 

g.    That the development must be completed within 3 years from the date of the approval granted by the Harbour Board.