To consider a report of the Director of Culture, Communities and Business Services setting out an application for Harbour Works Consent.
Additional documents:
Minutes:
The Board considered the report of the Director of Culture, Communities and Business Services setting out an application for Harbour Works Consent.
RESOLVED:
That the River Hamble Harbour Board approves the Harbour Works Consent for the proposal set out in paragraph 4 of this report and subject to the following conditions:
i. The proposal is to be built in accordance with the details, plans and
method set out in paragraph 5.
ii. The applicant should ensure that only coatings and treatments that are
suitable for use in the marine environment are used in accordance with
best environmental practice. All reasonable precautions will be
undertaken to ensure no pollutants enter the waterbody.
iii. The applicant should ensure that all equipment, temporary structures,
waste and/or debris associated with the licensed activities is removed
upon completion of the licensed activities.
iv. The development must be completed within 3 years from the date of the approval granted by the Harbour Board.
To consider a report of the Director of Culture, Communities and Business Services setting out an application for Harbour Works Consent.
Additional documents:
Minutes:
The Committee considered the report of the Director of Culture, Communities and Business Services setting out an application for Harbour Works Consent.
RESOLVED:
That the River Hamble Harbour Management Committee recommends to the
River Hamble Harbour Board to approve Harbour Works Consent for the
proposal set out in paragraph 4 of this report and subject to the following
conditions:
a) The proposal is to be built in accordance with the details, plans and
method set out in paragraph 5.
b) The applicant should ensure that only coatings and treatments that are
suitable for use in the marine environment are used in accordance with
best environmental practice. All reasonable precautions will be
undertaken to ensure no pollutants enter the waterbody.
c) The applicant should ensure that all equipment, temporary structures,
waste and/or debris associated with the licensed activities is removed
upon completion of the licensed activities.
d) The development must be completed within 3 years from the date of the approval granted by the Harbour Board.