226 Grunden Sand and Gravel Ltd. Frith End Sand Quarry Frith End Bordon PDF 1 MB
To consider a report of the Director of Economy, Transport and Environment regarding Variation of Condition 1 of Planning Permission 30633/034 to extend the time period of extraction to 31 December 2022 and completion of restoration within a further period of 2 years at Grunden Sand and Gravel Ltd., Frith End Sand Quarry, Frith End, Bordon (Application No. 30633/038) (Site Ref:EH121).
Additional documents:
Minutes:
Variation of condition 1 of Planning Permission 30633/034 to extend the time period of extraction to 31 December 2022 and completion of restoration within a further period of 2 years at Grundon Sand and Gravel Ltd Frith End Sand Quarry, Frith End, Bordon GU35 0QR (No. 30633/038) (Site Ref: EH121)
The Committee received a report from the Head of Strategic Planning (item 7 in the minute book) regarding an extension of time for works at a quarry at Frith End in Bordon.
The officer introduced
the item, showing the Committee aerial photos and footage from the
site. On a plan of the site it was indicated which areas had been
processed and were due for restoration along with those that still
needed to be extracted. It was anticipated that there was
approximately 120,000tonnes of mineral still remaining. Flooding
that had occurred following a burst riverbank and issues around
Covid had meant that that more time was
now required to complete the work on site and an extension to time
was being sought.
The Committee received three deputations on this item. Brian Davey
addressed the Committee as a local resident and had concerns over
planning creep on site and felt that the extension of time was
longer than what should be necessary for a 10 month delay. There
was also fear that approval of the extension would lead on to
further requests and expansion.
Stewart Mitchell addressed the Committee on behalf of the applicant
to reassure that the request was only to assist with the delays to
existing work and the site was crucial for providing mineral for
Hampshire.
Councillor Mark Kemp-Gee spoke as the local Member and thanked
Grundons for the liaison panel that had
proved successful and well managed, and also for their support of
the local Kingsley Centre, which had continued throughout lockdown.
Cllr Kemp-Gee also confirmed that the site had flooded before and
shared residents concerns that a two year extension seemed a long
time.
During questions of
the officers, the following points were clarified:
· The extraction at the site included both soft and silica sand
· Future development had not been proposed and was irrelevant to the application being sought in any case
· The flooding of the river had not been caused by the quarry
During debate, Members
agreed that the flooding on site was something that would need to
be addressed by the Environment Agency and that the application
should only be able to complete the works previously sought for in
the original permission.
It was confirmed that an update report had been circulated, which
summarised updates from County Ecology, the Flood Risk permit and
representations.
RESOLVED:
Planning
permission was granted subject to the update report and conditions
listed in Appendix A.
Voting:
Favour: 16 (unanimous)